A perspective before the proposal

I think it’s very important to have a feedback loop, where you’re constantly thinking about what you’ve done and how you could be doing it better.

— Elon MuskInterview with Lance Ulanoff · Mashable, 2012

For Unit-IV, that discipline means questioning every operating unit — and engineering the monthly net power bill 51% lower.

Enter the proposal
Suryamanu × Mohan Spintex · Solar + BESS EPC proposal

Unit-IV power-cost
transformation

₹0.00 Cr / month

Gross bill savings — every month.

₹3.76 lakh a day · ₹12.79 Cr year-1 net of O&M

0.0%

18-year project IRR

₹36.9 Cr NPV at a 10% discount

The offer12 MW AC solar · 40 MW BESS · AI-powered EMS
−0%Grid energy displaced96,973 → 39,296 units/day
ZeroGrid draw at T2 & T5 peaksBESS covers both premium windows
0.0 yearsSimple payback₹12.79 Cr year-1 net saving
₹0.0 CrEPC investment basis₹2.7 Cr/MW solar · ₹1.3 Cr/MW BESS

Prepared by Suryamanu for Mohan Spintex · Consumer KRN4083 · modeled from the October 2026 electricity bill

See the value case

A 51% lower power bill, paid back in 6.6 years.

Suryamanu’s integrated solar, BESS and AI-EMS proposal · modeled from Mohan Spintex’s October 2026 electricity bill

Offered scope

01

12 MW AC solar

≈62,000 units generated each day

02

40 MW BESS

Two 20 MW blocks · peak-window dispatch

03

AI-powered EMS

Coordinates solar, grid and stored power

04

₹84.4 Cr EPC basis

₹2.7 Cr/MW solar · ₹1.3 Cr/MW BESS · 18-year investment case

Monthly net bill₹ crore
Today
₹2.22 Cr
Forecast
₹1.09 Cr
See how the bill changes

Forecast gross bill saving

₹2.22 Cr → ₹1.09 Cr · ₹3.76 lakh a day

₹1.13 Cr / month

Grid energy displaced

96,973 → 39,296 units/day · T2 and T5 grid draw zero

−59%

Simple payback

₹12.79 Cr year-1 net saving after O&M

6.6 years

18-year project IRR

₹197 Cr clear of capex · 3.3× money multiple

15.9%
One proposal links the current bill, engineered dispatch, investment returns and accountable EPC delivery.

Energy alone costs ₹5.57 lakh a day — 75% of the net bill.

October 2026 · full charge schedule with a per-day column (30-day cycle) · every line reconciles to the bill

Switch the amount column between the billing month and its daily equivalent.

Charge headRate · basisUnitsAmount (₹)Note
Demand charges₹475 / kVA / month4,528.50 kVA21,51,037.50Recorded MD billed in full
Energy charges₹5.85 / kVAh28,58,8071,67,24,020.95Energy base — see net energy
TOD charges−₹0.75 / +₹1.50 by slot6 slots4,50,150.00Slot-wise workings below
FPPCA (Feb-2024)₹0.4619 / unit24,88,70011,49,530.53Fuel & power purchase adjustment
FPPCA (Jul-2026)₹0.3938 / unit28,59,90011,26,228.62Fuel & power purchase adjustment
Electricity duty₹0.06 / kWh29,05,3001,74,318.00On kWh consumption
Colony charges₹7.00 / unit50,4933,53,451.00Colony meter CL01
True-down (Mar-2025)−₹0.1343 / unit29,64,800−3,98,172.64Credit passed to consumer
Sub-total——2,17,30,563.96+ customer chg ₹2,813 · LPC ₹4,83,790.52 · ED interest ₹2,375.50
Net bill amount——2,22,19,543.00Payable on or before 18-Oct-2026
Sub-total ₹7.24 L/day + below-the-line ₹0.16 L/day = net ₹7.41 L/day (₹2,22,19,543); energy + demand are 87% of the sub-total.

96,843 kWh a day at 90.6% of contracted demand; PF near unity.

Meter cycle 01-Sep-2026 → 01-Oct-2026 · main meter APZ01095 · MF 1,000 · daily average = 30-day total ÷ 30

01

MD billed in full

Recorded 4,528.5 kVA against 5,000 kVA contracted — no exceedance; demand charged at ₹475/kVA on the recorded MD — ₹71,701 per day.

02

Power factor near unity

kVAh exceeds kWh by just 4,000 units (0.14%) — 133 units a day. Energy is billed on kVAh, so the gap costs ₹23,400 this month.

03

Colony netted out

Colony meter CL01 drew 50,493 units (1,683/day) — billed separately at ₹7.00/unit and excluded from energy-charge units.

90.6%

MD utilisation

Target 5,000 kVA contracted · actual 4,528.5 kVA recorded

0.9986

Power factor

kWh 29,05,300 · kVAh 29,09,300

45.9%

Off-peak share

T1+T3 = 13,34,800 units of 29,09,200 TOD total

96,843 kWh / day · 96,977 kVAh / day 1,683 colony units / day over the 30-day cycle
RegisterOpening 01-SepClosing 01-OctDifferenceMFNet consumption
kWh1,34,694.001,37,599.302,905.301,00029,05,300
kVAh1,35,183.001,38,092.302,909.301,00029,09,300
MD (kVA)—4.5285—1,0004,528.50
Demand headroom is 471.5 kVA; at PF 0.9986 the kVAh basis costs ₹780/day (₹23,400 in the month) — no penalty exposure.

Night slot T1 averages 24,480 units a day; peaks hold a third.

Six TOD registers, 01-Sep → 01-Oct 2026 · 30-day averages · TOD charges follow in the next section

01

Night slot T1 leads

7,34,400 units between 00:00–06:00 — 24,480 units/day, 25.2% of the day. The plant runs heaviest in the cheapest, rebated window.

02

Peaks hold a third

T2 (06–10) + T5 (18–22) together draw 9,67,500 units — 32,250 units/day, 33.3% — both carry a +₹1.50/unit surcharge.

03

Late night thins out

T6 (22–24) is the smallest register at 2,41,500 units — 8,050 units/day, 8.3% of the day.

96,973units / day

29.09 lakh units across the six registers

Daily consumption by TOD slotunits/day

T2 and T5 are the two premium windows; every unit moved out of them avoids the +₹1.50 surcharge.

44,493 units/day already sit in off-peak slots (45.9%), yet the 32,250 units/day in peaks drive the entire net TOD penalty.

Peak premiums outrun off-peak rebates — +₹15,005 a day net.

Slot units × TOD rate · per-day units and amounts are 30-day averages · surcharges in amber, rebates in ice blue

Net TOD amount by slot₹ / day
Slot · windowUnits (kWh)Units / dayRate (₹/unit)Amount (₹)₹ / dayNote
T1 · 00–06:007,34,40024,480−0.75−5,50,800.00−18,360Off-peak rebate
T2 · 06–10:004,86,10016,203+1.50+7,29,150.00+24,305Morning peak surcharge
T3 · 10–15:006,00,40020,013−0.75−4,50,300.00−15,010Off-peak rebate
T4 · 15–18:003,65,40012,1800.000.000Flat — base tariff applies
T5 · 18–22:004,81,40016,047+1.50+7,22,100.00+24,070Evening peak surcharge
T6 · 22–24:002,41,5008,0500.000.000Flat — base tariff applies
Net TOD charges29,09,20096,973—+4,50,150.00+15,005Matches the bill line exactly
Premiums ₹48,375/day (T2+T5) vs rebates ₹33,370/day (T1+T3); shifting ~6,700 units/day from peaks to off-peak would neutralise the +₹15,005/day net penalty.

Net energy charges run ₹1.72 crore a month — ₹5.72 lakh a day.

Net energy charges = energy charges + TOD charges · October 2026, 30-day cycle · both components reconcile to the bill

01

Energy base

28,58,807 billed units × ₹5.85 = ₹1,67,24,020.95 a month — ₹5,57,467/day, reconciled to the bill energy-charge line.

02

TOD adder

Peak premiums less off-peak rebates add ₹4,50,150 a month — +₹15,005/day.

03

Effective energy rate

₹1.72 Cr over 29,05,300 kWh drawn — an effective ₹5.91 per kWh, about ₹0.06 above the flat ₹5.85 tariff.

ComponentPer month (₹)Per day (₹)
Energy charges (₹5.85 / kVAh)1,67,24,020.955,57,467
TOD charges (net of rebates)4,50,150.0015,005
Net energy charges1,71,74,170.955,72,472
Net energy charges · October 2026₹1,71,74,170.95 / month

= ₹5,72,472 / day · ₹23,853 / hour

77.3%of the ₹2.22 Cr net bill is net energy
Continue to the proposed system
Net energy is the largest cost line at ₹1.72 Cr/month — Suryamanu’s proposed solar-BESS dispatch follows

One integrated proposal: solar, two battery blocks, AI-EMS on watch 24/7.

12 MW AC solar + 2×20 MW BESS · priority, sequence and timing · continuous monitoring and fail-safe supervision

Proposed control architecture24 / 7
12 MW AC solar≈62,000 units/day33 kV gridbackup + T3 top-upAI-EMSpriority · sequence · timingBlock 1 · 20 MWT2 · next-day coverBlock 2 · 20 MWT5 · same-day coverUnit-IV factorycontinuous load
24/7 control loopsense → decide → dispatch → verify

Abnormal reading: alarm → isolate affected equipment → controlled grid fallback; final protection settings are confirmed during detailed engineering.

The proposal pairs energy savings with operating discipline: two independent storage blocks, continuous supervision and a defined fallback.

Suryamanu’s AI-EMS is an operating rulebook: priority, sequence, timing.

Dispatch logic for the 12 MW solar + 2×20 MW BESS · three governing rules run the day

01

Priority — Block 2 first

All charge goes to Block 2 until it is full (~11:35); only then does Block 1 charge (~12:20–15:00). The block serving tonight’s T5 peak is never left waiting.

02

Grid draw zero at peaks

Block 1 discharges across T2 (06–10) and Block 2 across T5 (18–22). In both windows the plant draws nothing from the grid — so no +₹1.50/unit premium is paid.

03

Cheap-window grid top-up

If solar surplus runs short, the EMS tops up from the grid only in the −₹0.75 rebate window (T3, 10:00–15:00): 560 kW for five hours — ₹5.10/unit instead of ₹7.35 peak power.

12:00
Block 2 full → Block 1 charging

Block 1 charges for the next morning’s T2 window.

B1 → T206:00–10:00
~11:35 · B2 full
~15:00 · B1 full
B2 → T518:00–22:00

Block 1 · 20 MW / 40 MWh

Discharges T2 06:00–10:00
Charges ~12:20–15:00

Block 2 · 20 MW / 40 MWh

Charges first — full ~11:35
Discharges T5 18:00–22:00

Priority charging protects tonight's T5 coverage; morning cover comes from Block 1; the grid is touched only when it is cheapest.

12 MW AC yields ~62,000 units a day — 64% of the plant’s draw.

15.6 MWp DC · ~4.0 kWh/kWp/day net of clipping · per-day estimates on the 30-day cycle

01

39,700 units peak at noon

64% of daily solar lands in T3 (10:00–15:00); the T2 shoulder adds 12,800 units, T4 another 9,500.

02

Direct vs storage split

28,148 units/day run the plant directly (midday load 4,035–8,400 kW); 33,852 units/day go into storage — 54% of generation is time-shifted to the peak windows.

03

Only 2,796 units of grid help

Storage needs 36,648 units in; solar supplies 33,852 — the EMS buys the shortfall only in the T3 rebate window.

5.17kWh/kWp/day

Equivalent AC-side yield (62,000 ÷ 12,000 kW)

Solar generation by TOD slotunits/day

62,000 units/day total · nothing outside daylight hours · 2,796 units/day of deliberate T3 grid top-up

62,000 units/day ≈ 18.6 lakh units/month — enough to carry both BESS blocks through the night and evening peaks with margin.

One day on the system: solar, grid and batteries in step.

Hourly profile, per-day average · solar · grid draw · BESS discharge · BESS charge

12:00560 kW grid
01

06:00 — Block 1 takes T2

4,035 kW from storage for four hours; grid draw falls to zero through the morning peak.

02

10:00–15:00 — solar day

Solar covers the load outright; surplus fills Block 2, then Block 1, with only 560 kW of grid top-up.

03

18:00 — Block 2 takes T5

4,012 kW from storage for four hours; the evening peak costs the plant nothing from the grid.

2zero-grid slots

T2 and T5 — 8 of 24 hours, 33% of the load

kW per hour · grid top-up 560 kW confined to 10:00–15:00 · BESS bars show charge (−) and discharge (+)

T2 and T5 become zero-grid slots; solar covers 60% of daily energy directly and via storage — losses are priced into the forecast.

Grid draw falls to 39,296 units a day — T2 and T5 go to zero.

Current vs forecast grid draw per TOD slot, units/day · ice bars show the displaced volume

01

Night slots unchanged

T1 (24,480) and T6 (8,050) stay on the grid — cheap, rebated, and outside solar hours.

02

Peaks fully displaced

T2 (−16,203) and T5 (−16,047) come entirely from the batteries. T3 shrinks 86% to 2,796 units of deliberate top-up; T4 falls 77% to 2,763 in the late-afternoon fade.

03

What the grid still carries

39,296 units/day = 41% of today — the night base load plus small daytime residuals.

−57,677units/day

Grid energy removed — 17.3 lakh units/month

Grid energy by TOD slotunits/day

Mid bars — current grid draw · ice bars — forecast grid draw after solar + BESS dispatch

−59% grid draw with zero consumption at both peaks; the money effect follows in the next two sections.

Net energy repriced: ₹5.72 lakh a day falls to ₹2.00 lakh.

Current vs forecast · per-day and per-month · same tariff base, same load — only the source of the units changes

01

TOD swings negative

Peak premiums of +₹48,375/day (T2+T5) drop out entirely; the small T3 top-up adds −₹2,097/day of extra rebate. Net TOD: +₹15,005 → −₹20,457/day.

02

Every shifted unit wins twice

A unit the BESS moves into T2/T5 is worth ₹7.35 at the meter; it was charged at ₹5.10 (or free solar) — the ₹2.25/unit spread is the arbitrage core of the case.

03

Losses are priced in

The 88% round-trip costs 4,398 units/day of solar; all figures below are net of it.

−₹1.12 Cr/ month

Net energy charges alone — 65% lower

Daily energy-cost comparison₹ / day
MetricCurrentForecastChange
Energy charges (₹/day)5,57,4672,20,475−60%
TOD charges (₹/day)+15,005−20,457rebate net
Net energy (₹/day)5,72,4722,00,018−65%
Net energy (₹/month)1,71,74,17160,00,534−65%
Effective rate (₹/kWh drawn)5.912.06on grid energy only

Forecast basis: 37,613 energy units/day (39,296 grid draw − 1,683 colony) × ₹5.85; TOD = T1 + T3 rebates on the new draw; solar capex/EMI not included — this is the tariff-side effect only.

Net energy ₹60.0 lakh/month vs ₹1.72 crore today — the full bill effect, including duty, follows next.

Forecast: the ₹2.22 crore net bill nearly halves to ₹1.09 crore.

Monthly net bill walk, current → forecast · demand, FPPCA, true-down, colony and below-the-line heads held constant

01

−₹1.01 Cr of energy

57,677 fewer grid units/day at ₹5.85 — the dominant saving, straight off the largest charge line.

02

−₹10.6 lakh of TOD

₹4.50 lakh of net premium becomes ₹6.14 lakh of net rebate — a ₹10.64 lakh swing per month.

03

Duty follows the units

Electricity duty at ₹0.06/kWh falls ₹1.03 lakh/month as grid draw shrinks; every other head is unchanged.

₹1.13 Cr/ month

Forecast saving — ₹3.76 lakh every day

Monthly net bill walk₹ crore

₹ crore per month · reductions in cyan · mid bars are the two bill totals

Estimates exclude solar capex/EMI and BESS degradation; actuals vary with irradiance and load.

₹1.09 Cr vs ₹2.22 Cr (−51%) — the case rests on three levers, all of them quantified from this month's bill.

₹84.4 crore in, ₹12.79 crore net annual saving — payback in 6.6 years.

Capex ₹2.7 Cr/MW solar · ₹1.3 Cr/MW BESS · 18-year life for both assets · O&M 0.4% solar / 0.5% BESS + ₹0.35 Cr EMS & insurance

Capex build-up — ₹84.4 Cr

ComponentMW₹ Cr/MW₹ Cr
Solar (12 MW AC)122.732.4
BESS (Block 1 + 2)401.352.0
Total project capex84.4
Solar · ₹32.4 Cr
BESS · ₹52.0 Cr

Year-1 O&M — ₹0.7396 Cr

Solar O&M — 0.4% of capex₹0.1296 Cr
BESS O&M — 0.5% of capex₹0.26 Cr
EMS, insurance & misc₹0.35 Cr
Total year-1 O&M₹0.7396 Cr

Basis: savings +3%/yr with tariff, −0.5%/yr degradation · O&M +5%/yr after year 1 · 18-year life · no mid-life replacement.

Gross bill saving

₹1.13 Cr a month · ₹3.76 lakh a day

₹13.53 Cr / year
Year-1 net cash saving after O&M

₹13.5325 Cr gross − ₹0.7396 Cr O&M = ₹12.7929 Cr

₹106.61 lakh/month · ₹3.50 lakh/day · before financing & tax
₹12.7929 Cr / year
Simple payback

Year-1 basis; cumulative cash turns positive in year 7

6.6 years
18-year IRR

NPV at a 10% discount = ₹36.9 Cr

15.9 %
₹84.4 Cr buys ₹12.79 Cr a year from day one — cumulative cash turns positive in year 7, followed by eleven more years of cash.

Break-even in year 7 — ₹197 crore clear of capex over 18 years.

Net cash flow in ₹ crore · savings escalate 3%/yr with tariff and degrade 0.5%/yr with the modules · no replacement within the 18-year life

01

₹12.79 Cr in year one

Gross saving ₹13.53 Cr less O&M ₹0.74 Cr; net cash climbs to ₹18.84 Cr by year 18 as tariff escalation outruns degradation.

02

Zero-crossing in year 7

Cumulative cash reaches ₹11.67 Cr at the end of year 7; discounted at 10%, the investment is fully recovered in year 10.

03

No replacement outflow

Solar and BESS are both modeled for 18 years, so no cell-replacement charge sits inside the projection; every operating year is cash-positive.

3.3×money multiple

₹282 Cr lifetime net cash vs ₹84.4 Cr capex

18-year project cash flowundiscounted ₹ crore
Selected yearYear 18

Gross ₹20.54 Cr · O&M ₹1.70 Cr · net ₹18.84 Cr · cumulative ₹197.33 Cr

Bars: annual net cash flow · line: cumulative position · click a year to inspect it

Full 18-year operation is assumed for both assets; financing, taxes and residual value are excluded.

View all 18 annual cash-flow rows
YearGross saving (₹ Cr)O&M (₹ Cr)Net cash (₹ Cr)Cumulative (₹ Cr)
113.530.7412.79-71.61
213.870.7813.09-58.51
314.210.8213.40-45.12
414.570.8613.71-31.41
514.930.9014.03-17.38
615.300.9414.36-3.02
715.680.9914.6911.67
816.071.0415.0326.70
916.471.0915.3842.07
1016.881.1515.7357.80
1117.301.2016.0973.90
1217.731.2616.4690.36
1318.171.3316.84107.20
1418.621.3917.22124.42
1519.081.4617.62142.04
1619.561.5418.02160.06
1720.041.6118.43178.49
1820.541.7018.84197.33
₹84.4 Cr capex → ₹282 Cr of lifetime net cash: ₹197 Cr clear of the investment — a 3.3× money multiple at a 15.9% IRR.

Payback stays inside ten years across every shock tested.

Simple payback and 18-year IRR · all 15 core scenarios clear the 10% hurdle · base case: ₹13.53 Cr/yr saving on ₹84.4 Cr capex

Interactive ROI explorerBase case
Simple payback6.6 years
18-year IRR15.9%
NPV @ 10%₹36.9 Cr
Cash clear of capex₹197 Cr
Clears the 10% hurdle by 5.9 percentage points.
Click any scenario to load itpayback · IRR
Saving \ Capex
-10%₹76.0 Cr
Base₹84.4 Cr
+10%₹92.8 Cr
+20%₹16.2 Cr/yr
+10%₹14.9 Cr/yr
Base₹13.5 Cr/yr
-10%₹12.2 Cr/yr
-20%₹10.8 Cr/yr

Payback = capex ÷ year-1 net saving · IRR over 18 years, with no mid-life replacement.

All fifteen core scenarios clear the 10% hurdle. Even a 20% saving shortfall combined with 10% higher capex pays back in 9.2 years and returns a 10.4% IRR.

Decision 1

Approve the ₹84.4 Cr EPC award

Base case pays back in 6.6 years and returns ≈3.3× capex over 18 years at a 15.9% IRR — above the 10% hurdle with margin.

Each month of delay forfeits ₹1.13 Cr — ₹3.8 lakh a day.
Decision 2

Lock tariff & banking terms before COD

Returns ride on the ₹5.85/kVAh + TOD structure and solar banking; secure long-term wheeling and banking commitments in the agreement.

A tariff re-opener remains the largest threat to returns.
₹84.4 Cr today buys ₹12.79 Cr a year — the returns survive every realistic shock; proceed to EPC and lock the tariff contractually.

Why Suryamanu qualifies for this Solar & BESS EPC project.

Commercial transparency · direct China manufacturing access · AI-enabled EMS · international project experience

One accountable EPC partner

Suryamanu brings together transparent commercial practices, direct access to China’s manufacturing ecosystem, intelligent energy-management technology and international project experience for Mohan Spintex’s integrated solar and battery storage system.

4 qualificationsVisible costs · controlled imports
Coordinated power · disciplined execution

Together, these capabilities offer commercial transparency, supply-chain control, intelligent power management and experienced project delivery.

01 / 04

Transparent procurement and billing

Clear and accountable procurement and billing give Mohan Spintex visibility into equipment costs, supplier charges, logistics and project expenditure — supporting budget control, simpler verification and lower risk of hidden costs.

What this means for Mohan Spintex

Better visibility into equipment costs, supplier charges, logistics and project expenditure.

Suryamanu combines commercial control, manufacturing access, intelligent dispatch and international execution in one EPC relationship.

One delivery chain connects the factory gate to Unit-IV’s EMS.

Proposed EPC discipline · direct sourcing · visible costs · documented imports · coordinated commissioning

Active linkChina manufacturing

Direct supplier coordination, quality oversight and commercial negotiation.

What Mohan Spintex receives

Commercial and supply-chain visibility

Equipment-cost and supplier-charge visibility; logistics and project-expenditure accountability; direct manufacturer coordination; quality oversight; export documentation and shipment monitoring through Suryamanu’s own Chinese company.

What Mohan Spintex receives

Technical and project-delivery coordination

AI-enabled coordination of solar generation, charging, discharging, grid interaction and stored-power use; practical problem-solving and disciplined execution by a team experienced across international markets, global suppliers and technical requirements.

Suryamanu’s China presence and international team reduce hand-offs; the EMS carries the same coordination into daily operations.

Three steps move the proposal from bill model to EPC award.

Joint validation before final BOQ, contract and procurement release · scope, responsibilities and commercial terms made explicit

01

Validate

Site survey, meter data, electrical interface, irradiance and load-profile validation.

02

Contract

Freeze BOQ, technical guarantees, commercial schedule and tariff/banking terms.

03

Execute

Procure, install, integrate the AI-EMS, commission and hand over.

Authorisation requested

Approve joint site & data validation

Nominate Mohan Spintex’s technical and finance teams; release available meter, SLD and load data for final engineering.

Each month of delay forfeits ₹1.13 Cr of modeled gross bill savings.
Commercial basis

Freeze the ₹84.4 Cr EPC scope

12 MW AC solar + 40 MW BESS + AI-EMS at offered capex rates; final BOQ, warranties, guarantees and delivery milestones to be contractualised.

Tariff and banking terms should be locked before COD.
Suryamanu is ready to convert this bill-based case into a site-engineered, contractually defined EPC project for Unit-IV.